Bidding for a logistics contract is a long and tedious process. First Global Logistics, our Egyptian member, is happy to report that after six months of bidding for the transport of Taba Substation Power. The executing agency and borrower for this project was the Egyptian Electricity Authority (EEA), a corporation under the Ministry of Electricity and Energy.
Photo Credit: First Global Logistics
The First Global Logistics has moved the first lot, which consisted of the MVAR -400 K.V. Shunt Reactor and its accessories. The shunt measured 5 x 3 x 3.5 meters and weighed 40 tons, while the accessories were both out of gauge and in gauge, which occupied a space of 350 CBM and weighed 80 tons.
The scope of work undertaken by the First Global Operations team included:
Photo Credit: First Global Logistics
This move via Sinai was one of the most critical aspects of this delivery. The ongoing insurgency in the region was a challenge that the experienced and seasoned team at First Global Logistics successfully overcame.
Related links
First Global Logistics Website
First Global Logistics Facebook
First Global Logistics LinkedIn